Progress at Campbelltown

28.07.2020
Client: Health Infrastructure
Architect: Billard Leece Partnership

Campbelltown Hospital Stage 2 works are starting to take shape. All foundations and site retention works have been completed for the Clinical Services Building, allowing all 12 jumpforms to make rapid progress with the first few post-tensioned floorplates following closely behind. Heading into the typical floorplates, this project is progressing well.

In addition, work on the Cancer Treatment Centre (CTC) is commencing, with foundations recently being poured and the 1-2m thick radiation-proof walls under construction.